SB 1 Baseline Agreement Process Statewide Teleconference Call

This Statewide Teleconference Call will provide an overview of the process for executing a Baseline Agreement, and is an opportunity for agencies receiving these funds to ask questions.
Tuesday, June 5, 2018
9:00 am – 11:00 am
Teleconference #: (877) 411-9748
Participant Code: 5283660
 
Questions during the call may also be submitted to: CTC@catc.ca.gov

Under the California Transportation Commission’s (Commission) SB 1 Accountability and Transparency Guidelines, projects adopted into the following programs are required to execute a Baseline Agreement:

  • Active Transportation Program – only projects with a total project cost of $25 million or greater or a total programmed amount of $10 million or greater.
  • Competitive Local Partnership Program – only projects with a total project cost of $25 million or greater or a total programmed amount of $10 million or greater.
  • Solutions for Congested Corridors – all projects
  • State Highway Operation and Protection Program – only projects with a total project cost of $50 million or greater, or a total programmed amount (in right-of-way and/or construction, support and capital cost) of $15 million or greater
  • Trade Corridor Enhancement Program – all projects

The SB 1 Accountability and Transparency Guidelines and the Baseline Agreement Template can be found on the Commission’s SB 1 implementation web page.

If you have any questions please contact Dawn Cheser, Associate Deputy Director at (916) 653-7665 or dawn.cheser@catc.ca.gov.<br>

More information about the California Transportation Commission can be found on the Commission web page.

Leave a Comment